General list of works
- calculation of parameters and necessary equipment;
- creation of the project and accompanying technical documentation;
- production of the LT unit according to the project;
- installation of refrigeration chambers at the customer's site;
- installation of the unit;
- switching of the system and automation;
- commissioning works were carried out;
- the first warranty service was carried out a month later;
System installation was completed in 9 days