Sausage factory “MyasovGrad”
МясовГрад
Refrigeration equipment
Production
Nikolaev
General list of works
- calculation of parameters and necessary equipment;
- creation of the project and accompanying technical documentation;
- production of the NT unit according to the project;
- installation of refrigerating chambers at the client's facility;
- installation of the unit;
- system switching and automation;
- start-up and adjustment work was carried out;
- a month later, the first warranty service was carried out;
System installation was completed in 11 days