Epicenter “FOOD MARKET”
Epicenter K
Installation of refrigeration equipment
Supermarkets
Khmelnitsky
General list of works
- calculation of parameters of the required equipment;
 - creation of the project and accompanying technical documentation;
 - production of units according to the project;
 - installation of refrigeration chambers and equipment at the customer's site;
 - setting up the monitoring system;
 - switching the system and automation;
 - commissioning work;
 - the first warranty service was carried out a month later;
 
System installation was completed 12 days