Client

Doyarushka

Types of work

Heat utilization systems

Business area

Heat utilization

City

Nikolaev

General list of works

  • calculation of parameters and necessary equipment;
  • creation of the project and accompanying technical documentation;
  • production of the NT unit according to the project;
  • installation of refrigerating chambers at the client's facility;
  • installation of the unit;
  • system switching and automation;
  • start-up and adjustment work was carried out;
  • a month later, the first warranty service was carried out;
System installation was completed in 12 days